The Change Equation
Case Study - e-Procurement in a Local Authority
You
can download and print this chapter from here
Here is a fully worked case study based on an assessment carried
out in a Local Authority. Some of the details have been omitted
for confidentiality reasons.
1. Introduction
The client is a Metropolitan Borough Council with 5,500 employees.
The e-Procurement Strategic Review was undertaken ahead of a project
planned to bring in an electronic marketplace and modernise the
purchase-to-pay (P2P) processes, most of which are still carried
out manually at present.
Some 1,000 managers and staff and around 7,500 suppliers are thought
to be involved in purchasing, invoice processing and payment for
goods and services – a spend of £200m last year.
The objective is to roll out e-procurement within 6 months. The
Executive Board had identified a number of potential risks in the
early planning of the project and the review was commissioned to
bring these into focus, assess their importance and develop strategies
to deal with them.
They included:
- A failure of a previous process improvement exercise
to deliver expected results
- The issue of compliance in a highly devolved organisation
- The significant levels of change over the past 2-3 years,
resulting in ‘change fatigue'
- The lack of strategic priority afforded to procurement
by dept heads and operational managers.
2. Approach
Imaginist carried out a review of:
- The project
- The organisation
- External factors, such as the relationship with key suppliers.
The review followed the INPACT assessment methodology, which focuses
on both process and culture transformation, identifying the main
barriers to success and recommending prioritised actions to address
these.
3. Results
The review identified that the lack of attention to both process
and culture issues would prejudice the realisation of the planned
e-procurement project benefits.
A calculation of the impact of the underlying barriers was presented
to the client, together with the reasons for this conclusion.
After discussion it was accepted that the project could take twice
as long to implement as planned (and cost 70% more) and that the
return in efficiency and cost savings may be as much as 80% below
expected levels. The reasoning and basis for this conclusion are
detailed in the remainder of the report. The impact assessment calculation
is summarised in Appendix A.
A programme of work to deal with the underlying barriers was put
in place, in line with the Action Plan in section 4 and the e-procurement
project roll-out plan was revised to allow for the greater complexity
revealed by the review.
4. The assessment
Organisation
Organisational Culture: The culture of an organisation
and the way it manages its processes are key to assessing how well
it will respond to change. The Organisational Culture model is used
to indicate the prevalent culture and the Process Management Capability
Maturity model is used to assess the way the organisation manages
its processes. From these analyses, an indication can be developed
of the organisation's capability to manage the changes.
Other indicators are then used to measure the potential for success
of the project, including the level of distrust across the organisation
and the robustness of the benefits realisation plan.
Using
the INPACT Organisational Capability tool, the management culture
of the organisation was found to be a mix of Pragmatist (1) and
Structuralist (2).
Within departments, there was evidence of a degree of pragmatism
(1) at managerial level, but this almost disappeared below managerial
level, with staff reluctant to act unless instructed to do so.
The well-defined structuralist (2) culture worked quite well but
with a strong tendency towards bureaucracy and ‘tribalism'. In this
Structuralist culture, managers and staff often hide behind the
rules and use them as reasons not to take the initiative. Change
is seen as largely negative, disruptive and to be avoided. Communication
is channelled up and down the management structure of the organisation,
with little real dialogue between staff and managers in different
departments. In this ‘tribal' culture, there is little sharing of
ideas and knowledge across the organisation, including within the
senior management team.
There was no clear alignment between individuals' aspirations and
the organisation's policies and strategic direction, which meant
that when changes were introduced, they tended to be imposed and
resented. In fact most interviewees, at all levels, felt overloaded
and under-resourced, not really coping with their day-to-day workload
and suffering the effects of several generations of process change
(each leaving unofficial and ad hoc work-arounds in their wake).
Although they recognised the need for cost savings, they could
not see how staffing levels could be reduced any further and still
enable them to carry out the jobs they wanted to do. Despite the
continual pressures there was still a level of commitment and concern
for the effect of this on the public, their ‘clients'. There was
also a level of frustration that nobody was asking them what would
work best.
This lack of empowerment at the staff level also flowed through
into the way managers made decisions – the process is slow and convoluted
and is informed by poor management information, which results in
high level policy never fully translating into action and short-term
decisions being taken rather, than well-informed, far-reaching and
creative decisions. Senior managers in this environment are necessarily
more interventionist than systemist (being able to steer from behind
and take the longer-term view).
The level of trust between managers and their staff was found to
be fairly good. There was less trust in the relationships between
the managers and the Senior Management Team, but that is not unusual.
However the levels of trust between departments was worryingly low
– distrust and lack of respect coloured almost all the relationships.
Cross-departmental communication and knowledge sharing was constrained
by this distrust and the implication of this situation is that the
take-up of e-procurement is likely to fall into the same patterns.
The degree to which managers and staff ‘own' the planned changes
correlates well to the amount of effort they are prepared to put
into making the changes happen and how well the project will generate
the expected improvements. The review did not find any real ownership
of the proposed changes in the affected departments - and this included
some Heads of Department, which is worrying. Managers with little
direct interest in procurement will not give the project sufficient
priority and their staff will not adopt the new processes, preferring
to carry on as before.
The concern among some managers is that the project will not achieve
the desired results but the organisation will have moved on to the
next change project and nothing will be done to improve performance
until budget constraints force another effort to move to the more
efficient processes.
Capability Maturity: on the Capability Maturity
Model (CMM) scale, the organisation is functioning at mostly level
2 (Controlled environment; repeatable, stable processes), with elements
of level 1 (Chaotic; ad hoc processes) and some areas at level 3
(Consistent Execution; defined, standard processes).
There
is no evidence of properly managed or measured processes (Level
4) although that is the level of maturity the organisation claims
for itself and that is the level of capability the project under
review requires. There is therefore a significant risk that it will
not succeed without significant changes in the way processes are
managed across the organisation.
One significant aspect of the immaturity of the organisation is
the lack of commitment from CEO and Board level through to operational
managers to making the project a success. Compliance to the new
automated procurement processes needs to be mandatory and unless
this is accepted by everyone involved in the changes, this project
is destined not to achieve its goals.
As would be expected in a predominantly CMM level 2 organisation,
visibility of existing process is poor - there has been little real
process analysis done at a sufficiently detailed level to understand
the implications of the automation of the P2P processes.
It is likely that quite a lot of the existing procurement processes
will still need to be undertaken manually, at least in part, and
particularly in complex service areas such as Social Services. Unless
this is addressed and decisions taken on how to manage the parallel
use of manual and automated processes, the tendency will be for
managers and staff to ignore the new automated processes, undermining
its roll-out.
The Project
The project was assessed for clarity of objectives, complexity,
robustness of its resource plan and how benefits were planned to
be realised.
Clarity of objectives: the research identified
a worrying lack of consistency in the perception of the objectives
of the project on the part of key stakeholders across the organisation.
Although there had been formal consultation, most managers and staff
had little interest in the project, only a vague idea of what was
going to happen and no real commitment to their part in realising
the intended benefits. There was general fear that it would mean
a loss of control and jobs.
Complexity of project: The project was assessed
using the INPACT Exponential Complexity Equation and came out with
a score putting it in the ‘Highly Complex Project' bracket. This
had not been anticipated by participants who had assumed it was
no higher than ‘Complex'. The advice for projects in the ‘Highly
Complex' bracket is: “Beyond this point your project is too complex
– break it down into separate projects and employ a programme manager”
Highly complex projects require full-time experienced programme
management and dedicated implementation resources, neither of which
were being allocated to this project – see below. They are unlikely
to be fully successful in an immature organisation i.e. lower than
CMM level 3, without injecting greater discipline and control over
the way the organisation manages its processes.
Robustness of Resource Plan: The project was
to be rolled out by a project board led by the procurement manager
with support from the IT department and the organisation's Business
Transformation Manager (who was also rolling out a CRM system).
There were no plans to allocate a full-time experienced project
manager to the project or to dedicate department resources to implementation
– in fact none of the project board were being allocated to work
full-time on the project. These resources are clearly inadequate
for a project of this complexity.
Benefits realisation: There was no benefits realisation
plan, despite quite substantial claims for cost savings and efficiency
improvement as a result of the modernisation of procurement. No
benchmarking had been carried out to ascertain actual costs of the
manual processes, relying on national published figures for the
business plan.
Automation and streamlining of P2P processes can lead to substantial
time savings, but only in small increments, across a large number
of staff. Tracking this is almost impossible, but it is possible
to task managers to redeploy this released time on to other operationally
key areas which are already subject to monthly or quarterly performance
targets - and track the improvement in these. This creates a healthy
‘pull' dynamic for the project.
The review found that Heads of Department and service heads were
resigned to cuts in budget to reflect the savings available when
the e-procurement system was implemented, but they were not being
held directly accountable for achieving or reporting efficiency
benefits and there were no plans to involve them in measuring improvements.
Without this involvement, efficiency benefits will not be realised
in practice.
Apart from improved process efficiency, the other two main areas
of benefit from automating and streamlining P2P processes are:
- price savings from the wider use of framework contracts
and online catalogues
- back office staff reductions from the simplification
of invoice handling.
Price savings depend on a sound analysis of spend and use of suppliers,
followed by dedicated effort to improving procurement performance.
None of this had not been done in preparation for the e-procurement
roll-out and did not seem to be in the project plan. Framework contracts
were in place for a few commodity areas but were not being widely
used. The procurement manager was waiting for the e-Marketplace
to be rolled out to give him the basis to start improving this position.
The problem with that was that it put the realisation of price benefits
at least 18 months to 2 years out. The procurement manager had not
been allocated an increase in the number of staff, nor did he have
skills in his existing team required to achieve these results.
Back office staff reductions depend on a two key actions, neither
of which appeared in the project plan:
- Simplification of the invoice matching process where
reliance can be put on 100% approval of purchase at the ordering
stage, i.e. mandatory take-up of
online purchase ordering, so nothing gets paid unless it has a
PO number.
- Working with suppliers to ensure they are able to accommodate
e-invoicing (which most can ' t) or adoption of a range of approaches
such as an ‘ order flip ' capability on the e-Marketplace, Government
Purchase cards and ‘ self-billing ' .
The lack of forward planning of these aspects of benefits realisation
puts in doubt the ability of the project to achieve the savings
set out in the business case.
External stakeholders
From scrutiny of the organisation's spend profile, there would
appear to be considerable scope for improvement in the cost effectiveness
of its procurement but this needs access to good management information
(which the current manual process does not provide) and the cooperation
of suppliers, who have to make the changes necessary at their end
for e-ordering and e-invoicing to be possible.
Supplier relationship: The organisation has little
knowledge of its suppliers, lacks a coherent supplier strategy,
does not monitor supplier performance and makes no attempt to develop
good, managed supplier relationships with key suppliers.
Less than 20% of the organisation's spend on goods and services
is contracted - and where contracts are in place, they are not actively
managed for best value. There are a few instances of collaborative
procurement with other public sector organisations and some use
of some framework contracts, including nationally negotiated government
contracts but these are not part of a systematic strategy.
Where there is greater attention to supplier performance, in some
specialist areas, the focus is on operational delivery of service,
rather than value for money and continuous improvement.
This not bode well for a relatively rapid move to e-ordering and
e-invoicing.
What needs to be done to deal with these barriers to success?
The Action Plan table in section 4 overleaf summarises the status
of the assessment elements, draws out the implications for the project
(including an indication of the impact on costs and timescales and
reduction in levels of benefits if the underlying causes are not
addressed) and suggests actions that might be taken to deal with
these.
The impact calculations are summarised in Appendix A. These are
not empirically researched figures – they are a consensus view based
on experience and discussion with the client, which ensures client
ownership of the assessment and the actions needed to avoid the
risks indicated.
Note: Many of the barriers impact on both costs and benefits: they
typically act both to delay the project (increasing costs and delaying
revenue benefits) and reduce take-up and the levels of benefit realised.
For the purposes of this assessment, impact is allocated either
to costs or benefits, where experience shows there to be the greater
impact.
Action Plan: The Organisation
| |
Component/
Status |
Implication |
Action required |
| 1 |
Management Culture
L (Pragmatist)/ (Structuralist)
|
The lack of alignment and empowerment
will reduce the level of benefits from this (and any other
change projects) by at least 10%. |
A1: A programme of interaction
and dialogue across the organisation is urgently needed to
improve the management culture. This needs to include increasing
top management visibility – see 4: Distrust Factor, below.
|
| 2 |
Capability Maturity
L (Mostly level 2, with
elements of level 1 and some areas at level 3)
|
The project needs a level of
organisational maturity which was not evidenced in the strategic
review.
Experience shows that this is a critical factor
and impacts both on time/costs and benefit realisation. The
latter is included here – a drop of at least 20%, maybe much
more. |
A2. It is crucial for the Board
to make take-up and compliance to the new processes mandatory.
The resources allocated are also not sufficient
- discussed in A7, below. The project itself could be used
to raise the level of capability maturity, if planned and
implemented with a greater involvement of stakeholders, see
A3, below. |
| 3 |
Visibility of process
L (Poor)
|
The new system will not impact
on all procurement, so staff will continue to work with manual
processes, particularly in complex service areas. This will
reduce the value of the new automated system, undermining
its roll-out.
The consequential lack of ownership of the changes
has been shown to add over 20% to project costs and timescales
- and in some cases it has effectively led to the demise of
the project. |
A3. A process mapping exercise
is required to identify those areas where the new e-Marketplace
and P2P system will not replace existing processes. Decisions
are then needed on how to deal with these to optimise efficiency
(including: ‘stop doing it unless it adds value' – LEAN).
The involvement of system users in the mapping
and redesign of processes has the benefit of embedding the
principles of process improvement and capability maturity.
|
| 4 |
Trust factor
L (Low across departments)
|
The low levels of trust will
slow down communication and response to calls for action -
it may even stop the project. At the very least they will
increase costs and timescales by at least 20%.
|
A4. Distrust and lack of respect
for managers and other departments needs to be investigated
and tackled as an urgent priority.
It often has its roots in poor cross-organisational
communication and the lack of top management visibility, which
can be addressed as part of a programme of interaction – see
A1 above. |
Action Plan: The Project
|
Component/
Status |
Implication
|
Action
required |
5 |
Clarity
of objectives
L (Poor) |
A lack of shared
understanding of the project's objectives reduces its priority
and may prejudice the chances of success. Correcting this
once the project has kicked off requires a significant effort,
delaying roll-out and adding up to 10% to costs. |
A5. Formal consultation
has been insufficient – further consultation and dialogue
is required with all stakeholders. Creation of a user panel
is strongly recommended to share responsibility for delivery
– see 8: Benefits Realisation, below |
6 |
Complexity
of project
H (Too complex) |
The project is too
complex to manage as it currently planned and resourced. It
will have to be broken down into a phased roll-out - the 6
month timescale is certainly unrealistic. The extended roll-out
will increase project costs (see 7, below) and delay realisation
of benefits, with an impact of 50% on year 1 revenues. 30%
has already been included under 1 and 2, leaving a net 20%
incremental impact |
A6. Implementation
should be re-planned in phases over a longer timescale and
benefit realisation brought in line.
The difficulty of introducing e-procurement
across a number of buyers and suppliers is best dealt with
by identifying and rolling out the priority spend categories
first. |
7 |
Robustness
of resource plan
L (Inadequate) |
The lack of full-time
project management, together with the lack of top management
commitment, strongly indicates a project that will not deliver
the expected results. Adding the necessary resource would
raise costs by 20% at external consultancy rates but may ensure
the project's success. |
A7. A full-time project
manager is needed, in addition to additional procurement resources
and skills to tackle supplier as well as buyer take-up. Unless
these resources can be found in-house, they should be brought
in using external experience and skills to accelerate the
pace of the project. The earlier realisation of savings should
pay for the additional costs. |
8 |
Benefits
Realisation
L (No plan) |
A significant proportion
of the expected benefits from a modernisation project come
from efficiency savings that are only achieved if managers
redeploy released resources in their department. 40% of the
project's cashable savings in year 1 was from process improvement.
Given the lack of benefits realisation planning, the authority
will be lucky to realise half of this. |
A8. Operational managers
need to be made accountable, as user representatives in the
project, for adopting the new processes and redeploying staff
to release resources and drive increased productivity in their
departments. Use existing key service targets to measure improvements,
rather than trying to monitor time savings. |
9 |
Relationship
with suppliers
L (Poor) |
The lack of knowledge
about the supplier base and lack of contract performance management
means that there is not the foundation of trust needed to
engage suppliers and get their co-operation to make the necessary
changes.
The impact of this on project timescales can
be significant – but even more critically, streamlining of
invoicing reduces accounts payable headcount, which can make
up a third of the potential gains from e-procurement. Although
this only comprised 20% of projected revenue savings in year
1, we would not expect to see more than half of this being
realised, and that will come more from budget cuts than as
a result of the project. |
A9. A rationalisation
of the supply base needs to be carried out before implementation
of the e-Marketplace to avoid having to load 7,500 suppliers'
details and to take advantage of suppliers already on the
e-Marketplace.
This requires an analysis and cleansing of the
supplier database, which should be carried out by an external
service provider to ensure that key data is appended (e.g.
impact on local suppliers).
A10. A communication programme is then needed
to ensure that all the key suppliers are ready and able to
accept e-orders and, where possible, issue e-invoices.
A11. Finally, a supplier adoption plan needs
to be put in place to bring key suppliers on board as the
system is rolled out to buyers.
A12. It is strongly recommended that an e-contract
management system is brought in to improve contract management
and supplier performance. |
Click here if you want
to read more of Peter's book
|